BakerHostetler - Washington, DC

This project required removal of a main building column to suit the desires of the client for a large unobstructed meeting space. The column was below the building mechanical yard and required careful coordination to provide the correct structural framing to support the roof slab and mechanical equipment on the roof. Our work included all structural design and the planning for the temporary jacking of the new double beams to transfer the load from the column to the new beams.

Project Numbers

Square Footage

Structural Steel Design and Construction Administration

Services

Project Gallery

Click on photo below to see full gallery of photos

Baker Hosteltler
Baker Hosteltler

Double steel beam reinforcing installed for column removal.

Baker Hosteltler
Baker Hosteltler

Temporary jacking operations to load the W24 beams prior to concrete column removal.

Baker Hosteltler
Baker Hosteltler

Large connections are required to transfer the load from the new double W24 to the existing adjacent columns.